TUK020 wrote:In early August, I signed up to "Surrey Solar Together" - a bulk purchase deal organised by Surrey County Council, and paid my £150 deposit, and got an indicative quote by mail. Guy came to see me about a week later, agreed details, confirmed the quote and scheduled the installation/scaffolding etc for about 10 days later.
What I got:
12 panels each of 400W nominal peak = 4.8kW
Wire mesh around panels to prevent birds nesting/squirrels etc (this was a highly recommended extra)
12 optimisers (chimney in the middle provides variable shading during the day)
3.7kW inverter (the thing that converts AD/DC and vice versa)
9.6kWh battery (double size than standard at my request). These don't give full capacity - they discharge to a minimum of 10% power.
Solar boost (generated power goes to serving domestic consumption first, charging battery second, boosting the immersion heater third, and only exporting to the grid fourth)
Control panel and logging
Scaffolding (3 story house) & Installation
Price: £9500:
Installation experience:
Scaffolding went in without problem
Electrician turned up on appointed day and did all of the electrical stuff without problems (routing of cabling from panels to battery/inverter was quite tricky, but they did a good job). Roofer was ill that day but turned up the following day and did all the panels then.
They left the scaffolding up for another 10 days to ensure there were no problems - this was a bit of a pain.
Overall, installation was very good - minor but infuriating issue was the mess up of the house WiFi. I had been worried about range from the study WiFi at the opposite end of the house to the garage, so the electrician put in a WiFi booster which then turned out to mess up the 2.4GHz band of the dual band WiFi. I would up redoing my WiFi later with a mesh system, and so got rid of this.
Second irritation was finding 3 nails left on the drive - could have been an unnecessary puncture.
Overall the install was good. Got the electrician to talk me through exactly what he had done on wiring & system installation, and he clearly knew his stuff.
Other relevant info:
I have an EV, and a home EV charger point already installed
I have an Octopus tariff designed for EV users - 25p/kWh standard rate, and 8p/kWh cheap rate between the hours of 00.30-05.30.
Because of this tariff, my export rate to the grid with Octopus is limited to my cheap rate - 8p.
Large house, multiple occupants, dishwasher and washing machine run a lot. Big electricity user.
Heating and hot water is from gas boiler, except for immersion heater top up described above.
Set up:
I have a Growatt dashboard (the make of inverter) on line, and programmed the system so that the battery charges from the mains overnight at cheap rate (also when I am charging my car), and then the house runs from battery during the day. The battery discharges until the solar panels start generating (which then runs the house and recharges the batteries a bit) and then discharges again during the evening.
Installation faces south west. Solar generates between 09.30-04.30 (GMT) can be very variable according to cloud level.
Usage/generation 20/8-7/11:
Domestic consumption approx 2MWh over about 10 weeks.
Solar generation: 680kWh
Battery charge/discharge: 660kWh
Exported to grid: 148kWh
There is some overlap between the generation and discharge figures.
Very roughly - 1/3 of my electricity is solar generated (free marginal cost). 1/3 is electricity is bought at cheap rate, and used at expensive rate. The remainder is either charging the car at cheap rate, or using grid day/evening at standard rate.
Conclusions
Too early to tell is the models on which I based by 5.75 yr payback are correct - really need to see an annual solar generation figure.
The other thing is that these models are very sensitive to Electricity usage (this will probably reduce as kids leave home), and electricity prices (don't foresee these coming down much), and the continuation of off peak cheap rate tariffs (fairly safe bet given the peak to average demand patterns of the UK.
An early thought is that the payback from the batteries probably exceeds that of the panels - although this largely assumes you have forked out for the inverter as part of the panels.
This then leads to an interesting thought that the long term profitability of this set up will to some extent depend on the charge/dischgarge lifetime of the batteries (I pretty much fully discharge these every day)
So far so good
Thanks for this - I suspect my end price will end up similar - I'll have slightly more panels (16 v 14), similar battery size, a larger inverter, optimisers and bird mesh etc.
My scaffolding requirement will be 3 storey on one side and 2 storey on the other. Given there is no car in the property, having scaffolding sitting there for a while before/after installation taking up drive space and blocking access to the garage is really not an issue.
When I submitted the forms, I used my actual electric usage for the last 12 months and it was c5000kwH. The gas usage (CH) has dropped dramatically partly because the hot water on that property is coming from electric rather than gas.
My "site visit" is scheduled for the 3rd December which is when I am back in the UK so will report back after that with the final quote etc and I will also then become even more of a statistical obsessive than Paul when it comes to reviewing the data even though I don't live there anymore!
Some might ask why am I bothering doing the install given I don't live there anymore - and it's mainly purely selfish. I suspect 2 things - one the property will likely command more rental but I'm also sitting on GBP that takes me into higher rate tax on savings so little point keeping it in cash when I can't contribute to an ISA anymore (non UK resident), have already maxed out premium bonds, and have cash in EUR that is also paying interest albeit at a lower rate than GBP and is still deemed taxable in the UK which takes me over the savings allowance as to how/where it's held.