Energy firms fined after subsea cable delay pauses Scottish windfarms

#462155

Postby richfool » November 30th, 2021, 7:17 pm

Two energy companies will pay a record £158m fine after delays to a major subsea power cable bringing renewable energy from Scotland to England and Wales caused home energy bills to rise.

National Grid and Scottish Power agreed to pay the penalty after an investigation by the industry regulator found many of Scotland’s windfarms were paid to turn off on windy days because there was no way to transmit the clean electricity to areas of high energy demand in the south of the UK.

The £1.2bn power cable known as Western Link was expected to carry enough electricity to power 2m homes over 260 miles, mostly under water, from Scotland to England from late 2015, well ahead of its late 2017 deadline from the regulator.

But the project was dogged by delays and was only ready more than three years later, in the summer of 2019, to help the UK make better use of its renewable energy generation.

During the delay the cost of turning off windfarms, and running alternative power sources such as gas and coal plants, was ultimately shouldered by households through their energy bills.

https://uk.finance.yahoo.com/news/natio ... 03180.html